Many residents in BK 3 are losing their patience with SPNB (Syarikat Prasarana Negara Berhad), especially when they saw some LRT track preliminary work had started in our area.
There were drilling frames for soil investigation work at our area for quite some time now. At certain areas the workers had even started to do some digging work to lay the underground cables.
This morning there was a land surveyor doing some surveying at the green lung area. Obviously he was doing some surveying work for the new LRT extension.
The residents had actually met and talked to SPNB three times since the LRT track and station no. 5 issues arose.
Just a few days ago SPNB had told us their consultants are finalizing their alternative proposals with a few options regarding realignment of LRT track and possible relocation of station no. 5.
SPNB had given us assurance no actual construction work will begin until our issues are settled.
We were also told SPNB will submit their proposals to MPSJ some time next week. After which a meeting will be held between BK 3 residents, SPNB and MPSJ to discuss the issues. Eventually MPSJ will have the final say on all the proposals.
There is still a long way to go...
A big pile of sand at green lung area, and some digging work |
There were drilling frames for soil investigation work at our area for quite some time now. At certain areas the workers had even started to do some digging work to lay the underground cables.
Cable laying work |
This morning there was a land surveyor doing some surveying at the green lung area. Obviously he was doing some surveying work for the new LRT extension.
Land surveyor doing work and soil investigation work |
The residents had actually met and talked to SPNB three times since the LRT track and station no. 5 issues arose.
Just a few days ago SPNB had told us their consultants are finalizing their alternative proposals with a few options regarding realignment of LRT track and possible relocation of station no. 5.
SPNB had given us assurance no actual construction work will begin until our issues are settled.
We were also told SPNB will submit their proposals to MPSJ some time next week. After which a meeting will be held between BK 3 residents, SPNB and MPSJ to discuss the issues. Eventually MPSJ will have the final say on all the proposals.
There is still a long way to go...